Wastewater RAS Pump Investigations
Client Type
Council
End User
Council
Services
Design, Data Logging, Site investigation, Operation Support/Advice
Project Overview
A complaint of pumps not performing/ suspected cavitation issues was reported at a wastewater treatment plant. The total flow of the pumps is ~200l/s. After site investigation using monitoring equipment, and data analysis, options were presented to the client to improve the performance of the pumps.
Key Outputs
- On site testing
- High accuracy, data logging
- Data analysis
- Design
- Report Writing
- Recommendations
- Operation advice
Water Treatment Plant Commissioning
Client Type
Contractor
End User
Private Company/Utility
Services
Commissioning, Problem Solving, Construction Management,Operator Training, Stakeholder Engagement.
Project Overview
Commission services for a project to upgraded a none complaint by adding UV disinfection and chlorine dosing and water quality instrumentation along with the controls system. The bore was part of a small network and supplies up to the flow rate of 75l/s.
Key Outputs
- Commission plan, and testing schedule
- Running of commissioning
- Problem Solving
- Operator Training
- Operation Support
- Technical support to Project Team
Irrigation Upgrades
Client Type
Irrigation Company
End User
Irrigation Company
Services
Design, Project Management, Construction Supervision, Problem Solving
Project Overview
Providing ongoing support for large irrigation company,
- Pipeline upgrades
- Pipework Design
- Contractor Management
- Stakeholder Managment
- Technical Support
- Problem Solving
- Data Logging
- Project Scoping
- Estimation
Portable Water Treatment Plants
Client Type
Contractor
End User
Government Agency
Services
Design, CAD, Project Management, Problem Solving, Commissioning
Project Overview
Sorted Water Solutions was tasked to design two water treatment plants which would go inline of a water source and water storage. It was conseptulised that the treatment process would be house in standard containers.
Sorted Water Solutions was responsible for
- Pipework design
- Equipment layout
- Detailed pipework drawings
- Detailed electrical containment and layout drawings
- Liaison with electrical contractor
- General design oversight of services around the container on site.
- Design of backwash settling tanks
The container design was developed from a performance specification to full construction drawings within a matter of weeks. The complete detail allowed for easy of construction and for the end client to understand the final product prior to commencing fabrication.
Water Treatment Plant Upgrades
Client Type
Contractor
End User
Government Agency
Services
Technical Support, Contractor Engagement, Construction Supervision, Construction Documentation
Project Overview
Providing technical support to a project upgrading a large water treatment plant in NZ. Technical support around mechanical works packages such as planning shut down cut-in plans up to DN1800 pipe on public distribution.
Key Outputs
- Quality Assurance documentation
- Sub-Contractor engagement
- Construction Supervision
- Writing of work instructions and methodologies
Irrigation Scheme Design/Upgrade
Client Type
Government Agency
End User
Government Agency
Services
Design, Project Management, Tendering
Project Overview
Sorted Water Solutions was contracted to design an upgrade to an existing wastewater treatment plant to irrigate final effluent to waste. This required a new pump station to be housed at the treatment plant along with pipelines to existing farm irrigation infrastructure.
Key Outputs
- Pump station design
- Mechanical pipewokr
- Upgrade to existing
- Pipelines
- Electrical design management
- Project Management
- Tendering
Portable Wastewater Treatment Plant
Client Type
Contractor
End User
Government Agency
Services
Design
Project Overview
Provided with a process design and equipment sections the development to detail design for construction of mechanical pipework, equipment and electrical layout was provided by Sorted Water Solutions. The construction timeline was very tight with the design time of only a number of weeks. Because of the detailed nature of the drawing the manufacture was almost seamless and able to be completed in a matter of weeks.
Key Outputs
- Mechanical Layout
- Pipework design
- Electrical containment
- Access Systems
- Walkways
- Detailed Design Drawings